Queen Victoria Street

Overview

Rooftop Solar at 99 Queen Victoria Street

  • Maze Engineering Solutions appointed MD Electrical to install solar panels on the office building’s flat roof.
  • The design had to preserve the sightline from St Paul’s Cathedral to the River Thames.
  • The installation was completed in December 2025.

Installation & Delivery

  • Installed 112 Eurener 580 W panels and one Solis 60K inverter.
  • Mounted 68 panels facing south at 10° using the ValkPro+ ballasted system.
  • Laid the other 44 panels flat to preserve the sightline.

Project Outcome

  • Delivered approximately 65 kWp of rooftop solar capacity while meeting the sightline requirement.
  • The system is estimated to generate 58,500 kWh and avoid 11,320 kg of CO₂ per year.

About the Project

Location

City of London

System size

Approximately 65 kWp

Annual Generation

58,500 kWh/year

Number Of Panels

112

CO2 Emissions Avoided

11,320 kg/year

Project Gallery